Jordan's Grove Road Bridge Replacement

◄ Back
February 11, 2019 2:11 PM

Jordan's Grove Road Project Update

The bridge replacement project on Jordans Grove Road was let on March 19, 2019 and the project was awarded to A.M. Cohron & Sons, Inc. of Atlantic, Iowa for a cost of $1,969,450.47. The bridge is over the Wapsipinicon River and a project schedule is not known at this time.

Facebook Twitter Email

Latest Update:

November 13, 2020 2:22 PM

The Jordan's Grove Road bridge is complete and the road will be open to all traffic at 4:00 today. Thank you for your cooperation throughout this project.

Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

View All Updates
November 5, 2020 12:41 PM

The bridge is scheduled to be open on Friday 13th to all traffic. Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

October 28, 2020 6:33 AM

The project is getting close to being finished. The completion date has been adjusted to the week of November 23rd.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)